The size of the biogas plant is to be decided based on availability of raw material. It is generally said that, average cattle yield is about 10 kg dung per day. For eg. the average gas production from dung may be taken as 40 lit/kg. of fresh dung. The total dung required for production of 3 m3 biogas is 3/0.04= 75 kgs. Hence, a minimum of 4 cattle